As construction continues apace here are some headline stats from the work we have completed so far:
180 wagons on and off the site moving earth during peak periods
Each wagon carried 20 tonnes of earth per journey during peak 2 week period
1,750 cubic metres of concrete has been used for the foundations
A further 1,000 cubic metres of concrete has been used for the slabs
Our green energy smart tech site cabin uses solar power and will reduce energy consumption by 50%
Other News
Management Team Expands Ahead of Summer Opening
(L-R) Adrian Field (Centre Manager), Hannah Swithenbank (Marketing and Engagement Manager) and Paul Lacey (Operations Manager) Leading regional developer Robert Hitchins Ltd announces the...
Creating Employment Opportunities at Cotswolds Designer Outlet
Bouygues UK is currently building the Cotswolds Designer Outlet and alongside our construction activities, we are thrilled to be working with Gloucester and Tewkesbury...
THERE IS NOTHING ECONOMY ABOUT THE LOCAL ECONOMY OF TEWKESBURY.
There is nothing economy about the local economy of Tewkesbury. As new figures are released from the 2021 census we are taking a look at 7 magnificent stats from our immediate catchment....